AT A GLANCE - GIANT MINE REMEDIATION PROJECT ROLLOUT

Parsons will develop the schedule and procurement strategy, also known as the Project Implementation Plan, for the Giant Mine Remediation Project. The types of activities, organized by major component, are as follows:

  • Underground mine workings
  • Freeze program 
  • Open pit mine workings
  • Contaminated soils and sediments
  • Baker Creek and surface water drainage
  • Tailings Containment Areas 
  • Borrow material
  • Water Treatment Plant and outfall systems 
  • Buildings and site infrastructure
  • Landfill 

For more information on the Closure and Reclamation Plan, and work activities discussed therein, please contact Crown Indigenous Relations and Northern Affairs Canada at 867-669-2426 or email giantmine@aandc.gc.ca